Storage tanks – CLC POWER - BANGLADESH

MAISHA GROUP, located in the centre of the capital city of Dhaka, is a large Bangladeshi consortium active in power generation (through CLC POWER Cy. Ltd.), real estate, property development and other infrastructure projects like expressways and Bus Rapid Transit (www.maishagroup.com).

In 2018, after consultation with 4D Construction and Consultancy, they decided to completely refurbish the steel structures of a 1st power plant, the 108 MW WASHPUR diesel power station (Keranigonj, Dhaka), and awarded the contract to ZINGAMETALL (Bangladesh) (www.zinga.bd).

Condition before surface preparation & application of ZINGA

The works started in March 2018.

Applying the 1st layer of ZINGA 60 – 80 µm DFT by brush & roller

Application of PU topcoat 50 – 60 µm DFT & delivery to the client CLC POWER in November 2020

System:

Surface preparation:

“Satblast” vapour blast to SA 2.5

ZINGA 60 – 80 µm DFT (by brush & roller)

Local PU topcoat 50 – 60 µm DFT