RAILS – SBS TRANSIT & SMRT - SINGAPORE
RAILS – SBS TRANSIT & SMRT - SINGAPORE
Singapore's MRT (Mass Rapid Transit) infrastructure is built, operated, and managed in accordance with a hybridised quasi-nationalised regulatory framework called the New Rail Financing Framework (NRFF), in which the lines are constructed, and the assets owned by the LTA - Land Transport Authority, a statutory board of the Government of Singapore. The Land Transport Authority allocates operating concessions to two for-profit private corporations, namely SMRT (Singapore Mass Rapid Transit) and SBS TRANSIT (Singapore Bus Services Transit), both of which are responsible for asset maintenance on their respective lines. These operators also run bus and taxi services, thus facilitating the full integration of public transport services in Singapore.
Both were facing corrosion issues and started to consider ZINGA for the “Find & Fix Maintenance” program. After several comparative tests, they realized that it was better to adopt ZINGA as a Preventive Maintenance.
Under the “Find & Fix Maintenance” trials conducted since 2013 both SMRT and SBS TRANSIT have accepted that ZINGA was a better anti-corrosion system compared to the other coatings used. The rails are mainly produced by MITSUI, NIPPON RAILS (Japan) and TATA RAILS (France).
Since 2016 and until today all the SMRT and SBS TRANSIT rails are protected with ZINGA as unique system.
The rails are sandblasted and coated in the workshops of ABRACLEAN (Singapore) under the constant supervision of ZINGA (Singapore) Pte. Ltd.
System:
Surface preparation :
Sandblasting to SA 2.5 with Rz 50-70 µm
ZINGA 2 x 60 μm DFT